The year 2025 marks a period of powerful acceleration for Palm Manor—an urban area developed by GP.Invest in Phu Tho. Across the entire construction site, the project has been deployed synchronously, systematically, and continuously. This clearly demonstrates the developer’s determination to uphold commitments to progress and quality, while gradually shaping the landscape of a modern, livable urban area in the Northern Midlands region.
Expediting Construction Progress Project-Wide
Throughout 2025, Palm Manor maintained a high construction tempo with the regular presence of 350–400 staff, engineers, and workers operating continuously on site. Construction management has been strictly controlled to ensure safety, quality, and the timeline for every category, from technical infrastructure to landscaping and residential construction.
As a result, the project achieved several major milestones, clearly reflecting GP.Invest’s practical execution capabilities and professionalism as a developer.
Completing Infrastructure: The Foundation for a Synchronized Urban Area
One of Palm Manor’s standout highlights in 2025 was the completion of ground leveling across a 22-hectare area, creating a vital foundation for the synchronized implementation of infrastructure and residential construction.
In parallel, the internal landscaping and transportation systems saw intensive investment and completion, including:
-
14,000 m² of green parks, providing community and relaxation spaces for residents.
-
13,000 m² of water surface, contributing to microclimate regulation and enhancing the quality of the living environment.
-
36,000 m² of internal asphalt roads, seamlessly connecting sub-zones to ensure convenient and safe traffic flow.
The completion of technical infrastructure and landscaping right from the initial stages demonstrates the “Synchronized – Complete – Sustainable” urban development orientation that GP.Invest pursues at Palm Manor.
Accelerating Housing Construction, Ready for Resident Handover
Alongside infrastructure, residential construction at Palm Manor was also vigorously implemented. By the end of 2025, the project had commenced construction on 450 out of 678 units, of which 350 units were fully completed and eligible for handover to residents.
These homes are constructed according to uniform standards in architecture, technical specifications, and finishing quality, ensuring a comfortable and safe living space suited to the long-term settlement needs of local residents and young families in Phu Tho.
Heading Towards Phu Tho’s Most Vibrant and Livable Urban Area
Entering 2026, GP.Invest continues to push forward with the deployment of Palm Manor with the goal of finalizing the entirety of Phase 1, while simultaneously investing in the construction of key landmark facilities to gradually form a complete utility ecosystem for the urban area.
According to the plan, key upcoming projects to be implemented include:
-
Commercial Center, catering to the needs for shopping, services, and community activities.
-
GP Academy Bilingual Kindergarten, contributing to elevated educational quality and adding value to residents’ lives.
-
Service Building and supporting amenities, creating momentum to drive a vibrant urban lifestyle.
With tangible implementation progress, a long-term vision, and a strong commitment from the developer, Palm Manor is steadily affirming its position as the most modern, synchronized, and livable urban area in Phu Tho, contributing significantly to the urbanization process and elevating the regional landscape.